We are moving at such a fast pace that I cannot keep up with taking pictures to keep everyone up to speed on our progress. We are 90% finished with the green complex on 18 and we still have to construct the new fairway bunker and tee complex. We will have the green complex finished by the weekend and we are now also working on the 1st tees that are adjacent to the 18th green. We are hoping by middle of next week we are out of this area and start working on #12. We will do the tees of 18 in December.