Thursday, December 10, 2020

Progress Being Made on 5

 

The work on 5 has been progressing steadily despite some heavy rains to start.  This is a big project which includes rebuilding and shifting all the fairway and greenside bunkers, changing the fairway contours, reshaping parts of the fairway and draining the entire fairway.  The biggest part of the project is happening now with moving a lot of turf, reshaping areas and building new bunkers.  Once this is done, we will add all new drainage on the top portion of the fairway.

The last 80 yards of the hole is a complete rebuild to add more strategy to the hole and to divert water away from the green and bunkers.  We are also rebuilding the alternate tee area on the 6th hole as well.  With continued good weather we should be almost done with the big work in another 10 days.