Thursday, June 17, 2021

Fuel Tanks

 

We are officially underway with our above ground fuel tank project.  The footing for the tank pad is formed and electrical rough inspection is done.  Now the bollards are being installed and next week we will pour the tank pad.  Once the pad is cured, we will install the new tanks, wire them up and then make them operational.  At that point, we will then drain and remove the old underground storage tanks by our shop.  With the tanks located in this location, the fuel truck will not have to drive all the way up to our shop anymore and disrupt play.  While it may be a minor inconvenience for us it is a win win all around.