Sunday, February 28, 2021

Messy Cleanup Ahead

 


We are seeing now that the snow is melting that all the high spots that were exposed first were decimated by geese.   They literally ate the grass right to the dirt in spots and while the grass will recover, we will be pushing these areas along this spring to help them to start growing.  Unfortunately, they also left droppings everywhere that will be another headache to clean.  With the heavy snow, the dogs were trying all winter to chase them but they would return as soon as evening came.

Tuesday, January 26, 2021

Beneficial Tree Removals

 



With the frozen ground we were able to get 4 poor trees removed along the road to the pump house.  All 4 trees were adjacent to the power wires that feed our pump house.  As you can see these were no brainers to remove, especially what we encountered this past August with Tropical Storm Isaias.

Thursday, January 21, 2021

Tree Trimming

 

This was money well spent.  We are renting this lift for a month for the cost of a tree company to come in for 1 day to do pruning around the course.  Assistant Steve Gauli has been operating the lift and doing the majority of the pruning and already the trees look much cleaner.  By February he will have addressed most of our key in play trees and come spring the course will look much cleaner.

Sunday, January 17, 2021

5 Green Complex Progress


 We continue to make some progress on #5 despite the weather.  We have the left green side bunker left to shape and tie it into the alternate 6th tee.  Fairway drainage on the upper portion of the hole will begin this coming week.  Despite the amount of work involved in this project we can so far call it a success.  A lot of shaping occurred to divert water and drain the lower section of fairway properly.  Bunkers tie into features much better.  Fescue has been removed from all bunkers.  Despite over an inch of rain this week, and numerous heavy rain events since Thanksgiving, no water has entered any of the new bunkers which means they will require little maintenance moving forward and the bunkers will look and play better longer.  We are hoping to have the bunker shaped before the freeze that is coming.

Building Progress

 

The building in nearing completion.  Insulation will be blown into the attic area this week, then masons will begin to prepare the floor.  Garage doors to be installed and electric to go in last.  We are hoping the building will be done by mid February.

Thursday, December 24, 2020

Cold Storage Building


 Our new 3000 sq ft cold storage building located between 1 and 18 has made significant progress since we started a few weeks ago.  On the building side, we just have to add insulation, electric and the doors.  We will then do the concrete floor last, hopefully in January some time if the weather allows.  This building will allow us to store more equipment inside and free up space at our main maintenance facility.

Thursday, December 10, 2020

Progress Being Made on 5

 

The work on 5 has been progressing steadily despite some heavy rains to start.  This is a big project which includes rebuilding and shifting all the fairway and greenside bunkers, changing the fairway contours, reshaping parts of the fairway and draining the entire fairway.  The biggest part of the project is happening now with moving a lot of turf, reshaping areas and building new bunkers.  Once this is done, we will add all new drainage on the top portion of the fairway.

The last 80 yards of the hole is a complete rebuild to add more strategy to the hole and to divert water away from the green and bunkers.  We are also rebuilding the alternate tee area on the 6th hole as well.  With continued good weather we should be almost done with the big work in another 10 days.