Tuesday, April 3, 2018

Practice Green Project

The practice green project is underway.  While we stockpiled the necessary fill the past few weeks to complete the project, today was step 1 before we start shaping.  The cart path located behind 18 green was removed, all irrigation around 18 green was removed and the bunker sand is being pulled out along with liners.  The next step is to strip all sod around the green and we can start to shape in the new bunkers, green expansion and new practice green.  We decided to tie the new practice green into the surrounds of 18 green so it makes sense to finish all the work in this area now to avoid doing work twice and to keep costs down.  While this will keep us really busy the next 4-6 weeks, the finished product will be very good. 